GÖTTINGEN, GERMANY

Extension of the biomass combined heat and power plant
Göttingen, Germany

Project

  • Stadtwerke Göttingen – expansion of the biomass combined heat and power plant

  • Supply of the district heating network through wood combustion

  • Contract awarded to Special Solutions based on long-standing cooperation

  • Largest buffer storage tank order in the company’s history

Place assembly
Buffer tank
Pressure maintenance

Performance parameters

  • Volume: 200 m³ (incl. insulation)

  • Height: 19 m

Task

  • Energy buffering to ensure continuous supply

  • Peak-load coverage in the event of fluctuating wood combustion

  • Planning and coordination of transport, installation and connection

Product solution

  • Vertical 200 m³ buffer storage tank with insulation

  • Delivery including Reflex pressure-maintaining system

  • Installation in a very confined space using a special crane

  • Drilling template for foundation preparation

  • Inspection and approval of the welding procedure

Achieved goals

  • Successful installation and commissioning

  • Smooth cooperation between Sales, Engineering and the customer

  • Basis for internal further development of large-volume storage tanks in Wąbrzeźno